ROCHESTER PUBLIC UTILITIES PSA
(RPU) SHEET 1 OF 1
POWER SUPPLY ADJUSTMENT
APPLICATION: Applicable to all rate schedules
where there is a kWh charge.
1. The Power Supply Adjustment will be determined
on a quarterly basis with application to the
first revenue cycle in the months of February,
May, August and November.
2. The Power Supply Adjustment is determined
by calculating the average actual cost per
kWh of retail power supply from all sources
and subtracting the average planned cost per
kWh from all sources. All calculations will
be carried out to $.00001 per kWh. Power supply
cost includes the cost of purchased power
including the power supplier's energy cost
adjustments, the cost of fuel for self-generation,
and fees for regional power grid services.
3. The average planned cost per kWh will
be adjusted for each new calendar year.
4. The Power Supply Adjustment will be the
actual amount per kWh calculated in #2 above
in excess of the planned amount per kWh calculated
in #2 above. This dollar amount per kWh will
be added to each kWh of sales.
|